Teradata strongly recommends that air flow measurements be performed before and after equipment installation. As soon as the site for the system installation is confirmed and accessible, perform the initial air flow evaluations. After the equipment installation is completed, repeat the air flow evaluations to verify pre-installation measurements.

Additionally, perform temperature and humidity measurements for each cabinet after the equipment is in production to ensure that the operation of Teradata equipment meets the specifications in Environmental Requirements.