Preinstallation Checklist - Active Enterprise Data Warehouse

6750 Platform Product and Site Preparation Guide

Product
Active Enterprise Data Warehouse
Published
March 2018
Language
English (United States)
Last Update
2018-04-18
dita:mapPath
ras1471890041833.ditamap
dita:ditavalPath
6750.ditaval.ditaval
dita:id
jvo1471649303173
Product Category
Hardware
Step Instruction References
1 Site preparation task list completed Review the Site Preparation Task List in the appropriate Product and Site Preparation Guide. Be sure all items in that checklist have been completed and the site is ready for installation.
2 Site ID created For information on site ID creation, go to: Site ID Creation Guidelines
3 Staging checklist completed and returned to Flex Make sure that the customer, Customer Services, and the sales team all understand and are in agreement with the system configuration.
4 Teradata configuration confirmed Make sure that the customer, Customer Services, and the sales team all understand and are in agreement with the system configuration.
5 Change Control plan confirmed Make sure that a Teradata Change Control has been opened and that it has all necessary approvals. Also verify with the customer if they require an internal Change Control prior to installation.
6 Customer power and CRAC adequate Make sure that the system power and CRAC requirements are met and ready for installation at the customer site.

Refer to the appendixes in this guide.

7 Customer floor plan validated Make sure that the customer's floor plan for the system is still valid and ready for installation at the customer site.

Refer to the appendixes in this guide.

8 Environmental requirements met Make sure that the customer site meets all environmental requirements.

Refer to the appendixes in this guide.

9 Spare parts ordered When applicable, make sure appropriate spare parts are ordered and stored properly.
10 Remote connectivity availability verified Make sure ServiceConnect (SMWeb 10 or later) access is established.