System Load Configurations - Appliance for Hadoop

Appliance for Hadoop 5 Platform Product and Site Preparation Guide

Product
Appliance for Hadoop
Published
February 2018
Language
English (United States)
Last Update
2018-05-03
dita:mapPath
pgm1471885501602.ditamap
dita:ditavalPath
hadoop5.ditaval.ditaval
dita:id
axw1471650877780
Product Category
Hardware
All power receptacles at the site must be wired to support the rated load specified in Input Power Plugs and Receptacles.

Teradata power subsystems use load sharing by default. Sites can expect an approximate increase of 100% in load on the active line when the other source of power fails. That is, a source has 50% of the load to start with, and when AC is lost from the other source, the remaining 50% of the load transfers to the active source.

Products with four cords need special attention when plugging in at sites with redundant power to ensure proper operation if one power source fails.
  • If the cabinet uses four cords and has four AC feeder boxes, the cords from the two left-hand side AC feeder boxes go to one site source, and the cords from the two right-hand side AC feeder boxes go to the second site source.