Adding a Job Schedule - Teradata Viewpoint - Teradata Workload Management

Teradata® Viewpoint User Guide - 23.04

Deployment
VantageCloud
VantageCore
Edition
VMware
Enterprise
IntelliFlex
Lake
Product
Teradata Viewpoint
Teradata Workload Management
Release Number
23.04
Published
April 2023
ft:locale
en-US
ft:lastEdition
2023-05-05
dita:mapPath
cxb1678987903668.ditamap
dita:ditavalPath
tky1501004671670.ditaval
dita:id
B035-2206
Product Category
Analytical Ecosystem
You can add a job schedule to a collect or analyze job.
  1. From the Jobs tab, click next to a job and click Edit.
  2. Click the Schedule tab.
  3. Click Add Schedule.
  4. Under Schedule, specify when this job will run.
  5. [Optional] If a collect job, select the following options:
    Option Description
    Limit to Under Duration, specify the maximum amount of time you want the job to run.
    Resume collect list if not yet complete Under Options, select to enable the following options:
    • Select If complete, restart job to start a job from the beginning if all items on the previous collect list of the job have already been submitted.
    • Select If complete, do nothing to prevent the job from running if all items on the previous collect list of the job have already been submitted.
  6. Click OK.