Evaluating Air Flow | Teradata Vantage - Evaluating Air Flow - IntelliFlex Platforms - Teradata Vantage

Preparing Your Site For Teradata Vantageā„¢ Hardware - 1.4

Deployment
VantageCore
Edition
IntelliFlex
Product
IntelliFlex Platforms
Teradata Vantage
Release Number
1.4
Published
October 2022
Language
English (United States)
Last Update
2024-01-26
dita:mapPath
bjz1663242053526.ditamap
dita:ditavalPath
oqt1542232706976.ditaval
dita:id
gpk1556809249221
Product Category
Hardware
Teradata Vantage
  1. Before installation, lay down the vented and cutout tiles according to the floor layout.

    Floor tile layout - before and after
  2. Request that all dedicated computer room air conditioning (CRAC) units be turned on.
    This makes sure airflow characteristics above and below the raised floor are consistent before and after installation.
  3. Measure the flow rate from every vented tile.
    Heat load differences before and after installation produce measurement differences in temperature and humidity levels. Therefore, temperature and humidity measurements taken before installation are of limited use.
  4. Measure and record flow rates from tile cutouts that do not have brush seals.
    This allows you to understand the extent of air leakage.
  5. Compare the flow rate through vented tiles to the chilled air requirement guidelines.
    If the airflow measurements do not meet the environmental requirements, it may be necessary to rearrange the floor layout, or increase the number of vented tiles per cabinet.
  6. After the equipment installation is completed, repeat the air flow measurements to verify pre-installation measurements.