Site Load Configurations | Teradata Vantage - System Load Configurations - IntelliFlex Platforms - Teradata Vantage

Preparing Your Site For Teradata Vantageā„¢ Hardware - 2.5

Deployment
VantageCore
Edition
IntelliFlex
Product
IntelliFlex Platforms
Teradata Vantage
Release Number
2.5
Published
March 2024
ft:locale
en-US
ft:lastEdition
2024-04-26
dita:mapPath
ske1710762973120.ditamap
dita:ditavalPath
oqt1542232706976.ditaval
dita:id
gpk1556809249221
Product Category
Hardware
Teradata Vantage

Teradata power subsystems use load sharing by default. Sites can expect an approximate increase of 100% in load on the active line when the other source of power fails. A source has 50% of the load to start with, and when AC is lost from the other source, the remaining 50% of the load transfers to the active source.

Products with four cords need special attention when plugging in at sites with redundant power to make sure of proper operation if one power source fails.

If the cabinet uses four cords and has four AC feeder boxes, the cords from the two left-side AC feeder boxes go to one site source, and the cords from the two right-side AC feeder boxes go to the second site source.