ICOP Project Plan - Teradata IntelliCloud

Teradata® IntelliCloud™ Service Description: On-Premises

Product
Teradata IntelliCloud
Release Number
1.0
Published
June 2019
Language
English (United States)
Last Update
2019-06-22
dita:mapPath
rlz1548276531860.ditamap
dita:ditavalPath
quc1548790924228.ditaval
dita:id
rlz1548276531860
Product Category
Cloud

The ICOP project plan includes the parties defining the technical requirements, planning and building the IntelliCloud-managed infrastructure zone in the customer data center, and implementing the service. Teradata works with ICOP customers to jointly manage the project throughout the subscription term.

Defining Phase: Technical Requirements

Determine the following information:
  • Number of data centers
  • Active TCore and Customer Data Space (CDS) capacity
  • Reserve TCore and CDS capacity
  • Number of Teradata Vantage instances
  • Number of backup generations
  • Ecosystem application support
  • Business continuity elements

Defining Phase: Project Plan

  • Establish the project plan and timeline.
  • Assign project managers.

Building Phase

  • Finalize the network connectivity interface design.
  • Allocate floor plan space.
  • Configure Vantage instances for deployment.
  • Initiate purchase orders for equipment to support implementing the data center.

Implementing Phase

  • Deploy the IntelliCloud ecosystem.
  • Migrate data.