Use the Modify Execute Time command to change the execute time for a job with a Waiting status in the Scheduled Requests list.

  1. From the Scheduled Requests list of the Teradata Query Scheduler Administrator, select a job with a Waiting status.
  2. Do one of the following:
    • Click Options > Modify Execute Time.

    • Right-click the job to display a shortcut menu and click Modify Execute Time.

    The Change Start Time dialog box appears.

  3. Enter a new start time using the Hour and Minute boxes.
  4. Click OK to close the dialog box and return to the Teradata Query Scheduler Administrator.